It is most convenient for the standing steel casing to be placed horizontally on the reinforced concrete screw pile. This work procedure can be carried out in two ways: 1) The steel casing is placed on the screw pile by a special pseudoframe with a winch. 2) The screw pile is inserted into the steel casing in the inclined direction with any movable crane with corresponding weight.
The connection between the pipe shoe and the reinforced concrete pile body can be injected into the inner of the pile pipe shoe, and connected in advance, or in the foundation pit, the pile body and the standing steel sleeve directly into the pipe shoe for connection, the latter method, the interior of the pipe shoe must be filled with cement slurry, when the pile body is swept into the pipe shoe, The gap between the pile and the shoe can be filled with cement slurry.
After sinking the reinforced concrete screw pile fixed with pipe boots in the soil, pull out the standing steel sleeve, which can be used to sink the next screw pile.